Kitkatla WTP Upgrades
This project involved expanding and upgrading the wastewater treatment plant (WWTP) in Gitxaala. I was responsible for preparing the initial structural upgrade plans and developing a Class D cost estimate for the proposed expansion.
What I did
- Initiated discussions with process mechanical, electrical, and building mechanical disciplines to understand the full implications of the WWTP expansion on cost.
- Reviewed existing facility plans and analyzed relevant building codes and regulatory requirements to identify potential challenges and cost impacts early.
- Compiled a detailed cost spreadsheet by synthesizing input from all disciplines. Focused on identifying and quantifying the significant cost items.
- Organized a teleconference with the client to review and clarify the assumptions behind the cost estimate.
- Benchmarked the overall projected cost against cost-per-area metrics from the Altus Canadian Cost Guide.
- Issued the final Class D cost estimate to the client.
Outcome
- The client agreed with the proposed Class D cost estimate. This established a reliable financial baseline for the project.
- My estimate set the stage for continued involvement in providing progressively more accurate cost estimates as the project advances through later design stages.